paintschedule





Project Start:
Project Finish:
Thu 4/8/04
Thu 7/15/04


Tasks


ID
Task Name
DurationStartFinishResource Names% Complete
1
Matt's Crew
0 daysMon 4/12/04Mon 4/12/04 0%
2
Guerin-Project#4246
8 daysMon 4/12/04Wed 4/21/04 0%
3
Swindells-Project#4199
8 daysThu 4/22/04Mon 5/3/04 0%
4      
5
Joe's Crew
0 daysMon 4/12/04Mon 4/12/04 0%
6
Calkins
5 daysMon 4/12/04Fri 4/16/04 0%
7
Quinn
8 daysMon 4/19/04Wed 4/28/04 0%
8
Warranty
4 daysThu 4/29/04Tue 5/4/04 0%
9
Heislen-Project#4240
7 daysWed 5/5/04Thu 5/13/04 0%
10      
11
Angel's Crew
0 daysMon 4/12/04Mon 4/12/04 0%
12
Banker
3 daysMon 4/12/04Wed 4/14/04 0%
13
Slotter-Project#4200
6 daysThu 4/15/04Thu 4/22/04 0%
14
Harvard Green-Project#3817-9
15 daysFri 4/23/04Thu 5/13/04 0%
15
Harvard Green-Project#3817-6
15 daysFri 5/14/04Thu 6/3/04 0%
16
Harvard Green-Project#3817-2
15 daysFri 6/4/04Thu 6/24/04 0%
17
Harvard Green-Project#3817-7
15 daysFri 6/25/04Thu 7/15/04 0%
18      
19
Toni's Crew
0 daysMon 4/12/04Mon 4/12/04 0%
20
Rand-Project#4216
4 daysMon 4/12/04Thu 4/15/04 0%
21
Ciruelos
5 daysFri 4/16/04Thu 4/22/04 0%
22
Greenwalt-Project#4277
5 daysFri 4/23/04Thu 4/29/04 0%
23      
24      
25
Sadtler-Project#4258
8 daysMon 5/10/04Wed 5/19/04 0%
26
Bates-Project#4364
8 daysMon 5/10/04Wed 5/19/04 0%

Resources


IDNameGroupMax UnitsPeak Units

Assignments


Task IDTask NameResource NameWorkStartFinish% Work Complete